Guide to the laying of non-woven carpets

2019-07-31 15:44 Source:未知 Writer: Steven
   
Based on the problems that occurred during the installation of the customer feedback, the company summarized the installation process of the non-woven carpet, and avoided unnecessary loss and problems during installation.

    First, you need to prepare the carpet knife, trimming machine, pistol drill, cutter, scissors, needle-nosed pliers, paint brush rubber roller, iron, square ruler, ruler, hand hammer, steel nail, small nail, vacuum cleaner, garbage Barrels, plastic containers, steel rulers, fit feet, elastic powder bags, small lines, brooms, rubber wheels, light trucks, shovel, cotton and tool bags, slippers, etc. (depending on different construction conditions, please add them yourself) use).

  1.Process flow
Base treatment → elastic line, sleeve, division, positioning → cutting → nail barbed tape hanging tape → laying liner → laying → detail processing andcleaning

  2. Movable laying: refers to a method of sticking to the base layer without adhesive, that is, it is not fixed with the base layer, and it can be trimmed along the corner of the wall. Generally only suitable for the laying of decorative craft carpets.

  3. Fixed laying operation process:
    1) Base treatment: The base layer to be laid is generally cement floor, or it can be wood floor or other material floor. The surface is required to be smooth, smooth and clean. If there is oil, it must be cleaned with acetone or turpentine. If it is cement floor, it should have a certain strength, the water content is not more than 8%, and the surface leveling deviation is not more than 4mm.

    2) Elastic line, sleeve, division and positioning: The elastic line, sleeve and division shall be carried out strictly according to the design drawings for the specific requirements of different parts and rooms. If there are regulations and requirements as shown in the drawings, the construction shall be strictly according to the drawings. . If there is no specific requirement in the paper, it should be located symmetrically and the cable can be positioned and laid.

    3) Tailoring: Carpet cutting should be carried out in a relatively wide area. Be sure to measure the room size accurately and register the number one by one according to the room and the type of carpet used. Then, according to the size and shape of the room, the carpet material is cut off by a trimming machine. The length of each carpet is about 2 cm longer than the room, and the width is calculated by cutting the size of the edge line of the carpet. The elastic wire cuts off the edge part, and then the hand is pushed by the cutting knife to cut from the back of the carpet. After cutting it, it is rolled into a volume and numbered, and placed in the check room. The large-scale room should be cut at the construction site.

    4) Nail barbed tape: Behind the edge of the skirting board around the room or walkway, use high-strength cement nails to nail the barbed plate to the base layer (the nail is facing the wall) with a spacing of about 40cm. The barbed plate should be 8-10mm away from the skirting surface to facilitate nailing the barbed plate.

    5) Laying the liner: Use the point-adhesive method to apply 107 glue or polyvinyl acetate latex, stick it on the ground base layer, and leave the barbed board about 10mm.

    6) Laying carpet:
  a. Stitching the carpet: lay the cut carpet on the mat, then roll the carpet up and stitch it at the joint. After the stitching is completed, the plastic tape is applied to the stitching, the seam is not scratched or hoisted, and then the carpet is tiled, and the looper is used to make the pile stitching at the seam.

  b. Positioning and fixing the carpet: first fix one long side of the blanket on the barbed board, cover the underside of the skirting board, and stretch the carpet with carpet struts. When stretching, press the carpet support by hand, hit the carpet support with your knees, and push it from side to side. If it fails to level out again, it should be repeated until it is flattened. Then fix the carpet to another barbed plate and cover the burrs. The carpet that grew out was cut with a cutting knife. After stretching in one direction, stretch in the other direction until all four sides are fixed on the barbed plate.

  c. When laying the carpet, first apply the adhesive on the side of the room, then lay the pre-cut carpet, then use the carpet to stretch the sides; then brush the two adhesives along the wall to flatten the carpet. side.

    7) Detail processing and cleaning: pay attention to the treatment of door bead and door frame, walkway and foyer, floor and tube root, heating cover, slot box, walkway and toilet door, stair step and aisle
platform, inner door and outer door, different color carpet The cutting, fixing and covering work of the carpet at the junction and the skirting board must be firmly bonded, and there should be no exposure, such as replenishment and post-repair. After the carpet is laid, after fixing the closing strip, clean it with a vacuum cleaner and thoroughly clean the fluff from the carpet surface.

    Special Note:
1. The interior must be completed before the non-woven carpet is laid. All heavy equipment in the room has been in place and has been commissioned, operated, and verified to meet the eligibility criteria.

2. Laying the base layer of the non-woven carpet on the floor requires that the surface be smooth, smooth and clean. If there is oil, it must be cleaned with acetone or turpentine. If it is a cement floor, it should have a certain strength and the water content should not exceed 8%.

3. Non-woven carpets, liners and adhesives should be checked to check whether the quantity, variety, specifications, colors, patterns, etc. meet the design requirements. If they meet the requirements, they should be stored in a dry warehouse or room according to their varieties and specifications. . It is recommended to pre-lay, match, and number before use.

一、First, the skirting boards around the room, walkway, etc. to be laid should be prepared in advance. Construction process of the bottom of the skirting board

二、Second, should leave the ground about 8mm, so as to hide the burrs under the skirting board.

三、 Before the construction of a large area, the construction samples should be released first, and the samples should be made. After the quality inspection department has passed the appraisal, the construction can be organized according to the requirements of the sample.



Contact us

Co: Dezhou Wings Import And Export Co.,Ltd.
Add: Lingcheng Area, Dezhou City, Shandong Province, China. 253000.
Cel: +86-18506403738(WeChat)
Skype: Katherine-ZhengHao
QQ: 932770440
E-mail: kathy@wingsnonwoven.com


Quick Contact